Award
At its meeting of July 21, 2025 Council of the Corporation of the Town of Petawawa awarded Tender PW-14-2025 as follows:
Resolution #5 - Council Meeting - July 21, 2025
Moved by Murray Rutz
Seconded by Lisa Coutu
That Council approves the award of Tender PW-14-2025, Water Tower Rehabilitation, to the lowest bidder being C3 Group in the amount of $678,642.72 plus HST; and
That Council approves $31,200.00 for engineering design and construction administration costs; and
That Council approves a 10% contingency allowance in the amount of $67,864.27, for a total project cost of $777,706.99 excluding HST.
Carried
Staff Report
Report # PW-24-2025 - Chris Mantha, Director of Public Works
Recommendation:
That Council approves the award of Tender PW-14-2025, Water Tower Rehabilitation, to the lowest bidder being C3 Group in the amount of $678,642.72 plus HST; and
That Council approves $31,200.00 for engineering design and construction administration costs; and
That Council approves a 10% contingency allowance in the amount of $67,864.27, for a total project cost of $777,706.99 excluding HST.
Discussion:
The tender was prepared and advertised in a local paper, on our website and social media pages. Fourteen (14) general contractors picked up tender documents and three (3) bids were received on the closing date of July 15, 2025, at 2:00 p.m. This tender is to rehabilitate the water tower on Water Tower Road.
Contractors and Tender Price (excluding HST):
C3 Group - $678,642.72
Landmark Municipal Services - $1,029,600.00
BGL Contractors Corp. - $1,266,387.00
Financial Implication:
The estimated construction budget for this project was $958,320.00, excluding HST, and has been included in the approved 2025 budget. C3 Group’s bid of $678,642.72 is approximately 41% below the budget estimate.